BridgeNY Projects - Hill Blvd & Veterans Rd

The Town was awarded two (2) grants by the New York State Department of Transportation (NYSDOT) under the Bridge NY Program as detailed below: 

  1. A grant up to $820,000 was awarded for the Veterans Road Culvert Replacement over the Hallocks Mill Brook and is 100 percent reimbursable by NYSDOT.
  2. A grant up to $2,600,000 for the Hill Boulevard Bridge Replacement over the Tributary to Barger Brook and is 95 percent reimbursable by NYSDOT. 

As part of this project, the Town retained the services of WSP USA for engineering services, right-of-way acquisition and construction inspection of the two projects. During the design phase of work, the Town elected to combine both of the projects into one (1) set of bid documents.

After review of submitted bids with WSP, the Town Board awarded a contract to the low bidder, Transit Construction Corp. The total contract price is $2,995,000.

 

MONTHLY PROJECT STATUS REPORT -   JANUARY 2021

 

GENERAL PROJECT INFORMATION

ORIGINAL CONTRACT AMOUNT:  $2,995,000

  • HILL BLVD:            $2,176,166.35
  • VETERANS RD:      $    818,833.65

CONTRACTOR PAYMENTS TO DATE:        $571,475    (Estimate #3-   thru December '20)

PERCENTAGE OF COMPLETED WORK:       19.08 %

NOTICE TO PROCEED:                                9/28/20

ORIGINAL COMPLETION DATE:                 5/25/21  (240 Calendar  Days)

 

WORK PERFORMED IN JANUARY:

VETERANS RD: CLOSED VETERANS ROAD on January 4th in Yorktown, Heights (at Greenwood).

  1. Road Closure Duration is 3 Months. Motorists to Follow Posted Detour Route
  2. Constructed Stream Diversion System Across Veterans Rd
  3. Completed Excavation and Removed Existing Culvert Structure
  4. Completed Installation of New Precast Concrete Culvert Structure
  5. Began Installation of Water Main Below New Culvert

 

PROJECT ISSUES & MILESTONES:

  • Awaiting APPROVAL from Westchester County Health Dept for Hill Blvd Utility Relocations - Watermain and Sewer Mains
  • Approved Additional Water Main Cost Estimate for Veterans Rd & Hill Blvd

 

SCHEDULE OF WORK FOR FEBRUARY 2021:

VETERANS RD:

  1. Complete Installation of Water Main
  2. Complete Installation of Backfill Material Around New Culvert Structure
  3. Complete Construction of Culvert Headwalls
  4. Complete Installation of Culvert Railings
  5. Begin Reconstruction of Roadway

ADDITIONAL COST ITEMS TO THE PROJECT (Contract Reserve Fund)

  • Test Pits at Veterans Rd / Hill Blvd                                   $14,560
  • Additional Watermain Work (Monitoring  Stations)   $26,070

                                                                                              TOTAL:  $40,630

 

January 5th, 2021 Update

The water main relocation work at Veterans Road is scheduled to start on Thursday evening at 9 pm. There will be intermittent service interruptions to nearby property owners while this work is occurring.

 

MONTHLY PROJECT STATUS REPORT  -   DECEMBER 2020

 

GENERAL PROJECT INFORMATION

 

ORIGINAL CONTRACT AMOUNT:       $ 2,995,000

  • HILL BLVD:       $2,176,166.35
  • VETERANS RD:       $818,833.65

CONTRACTOR PAYMENTS TO DATE:    $169,570      (Estimate #2 – thru Nov. ’20)

PERCENTAGE COMPLETE:      5.66%

NOTICE TO PROCEED:     9/28/20

ORIGINAL COMPLETION DATE:   5/25/21  (240 Calendar Days)

 

WORK PERFORMED IN NOVEMBER:

 

VETERANS RD:   Completed Installation of Temporary Steel Sheeting

HILL BLVD:          Completed Installation of Temporary Steel Sheeting for Stream Diversion System

 

PROJECT ISSUES & MILESTONES:

 

  • Awaiting APPROVAL from Westchester County Health Dept for Hill Blvd Utility Relocations – Watermain and Sewer Mains
  • Additional Watermain Work at Both Locations  – Received Contractor Cost Estimate

 

SCHEDULE OF WORK FOR JANUARY 2020:

 

VETERANS RD:

 

  • CLOSE VETERANS RD at GREENWOOD ST on MONDAY, JANUARY 4th (Closure is 24 hrs per Day, 7 Days per Week for 3 MONTHS - Estimated Duration)​
  • Motorists to Follow Posted Sign Detour During Road Closure
  • Install Watermain Gate Valves (2 ea) at NIGHT – Week of January 4th
  • Construct Steam Diversion System Across Veterans Rd
  • Begin Excavation of Existing Culvert

 

ADDITIONAL COST ITEMS TO THE PROJECT ($120,000 Contract Reserve Fund)

 

Test Pits at Veterans Rd / Hill Blvd                                    $14,560
Additional Watermain Work (Monitoring Stations)       $26,070

TOTAL:           $40,630

 

MONTHLY PROJECT STATUS REPORT – OCTOBER/NOVEMBER 2020

GENERAL PROJECT INFORMATION
ORIGIINAL CONTRACT AMOUNT:                                                 $ 2,995,000
- HILL BLVD:              $2,176,166.35
- VETERANS RD:       $    818,833.65
CONTRACTOR PAYMENTS TO DATE:    $150,510      (Estimate #1 – thru Oct. ’20)
PERCENTAGE COMPLETE:                       5.03% 
NOTICE TO PROCEED:                       9/28/20
ORIGINAL COMPLETION DATE:       5/25/21  (240 Calendar Days)

WORK PERFORMED IN OCTOBER & NOVEMBER:
HILL BLVD:   
- Completed Clearing & Grubbing
- Completed Tee Removals
- Installed (Covered) Construction Signs for Detour
- Established Survey Control
- Dug Test Pits 
VETERANS RD:
- Completed Clearing & Grubbing
- Completed Tree Removals
- Installed (Covered) Construction Signs for Detour
- Established Survey Control
- Dug Test Pits
- Installed 3 VMS Boards

PROJECT ISSUES & MILESTONES
- Received Approval from WCHD for Veterans Rd Watermain Relocation (12/1/20)
- Awaiting Contractor Submittal of Cost Estimate for Additional Watermain Work (Both Culverts)

SCHEDULE OF WORK FOR DECEMBER 2020:
HILL BLVD:
- Complete installation of Temporary Steel Sheeting for Stream By-Pass System
VETERANS RD:
- Complete Installation of Temporary Steel Sheeting along South Side of Culvert
- Close Road and Implement Detour for Motorists (January 4th)
- Install Gate Valves to Isolate Existing Watermain (First Week of January)
 

For additional information please view the supporting documents linked below.

Click any thumbnail image to view a slideshow

Veterans Rd Culvert Construction
Veterans Rd Culvert Construction
Veterans Rd Culvert Construction
Veterans Rd Culvert Construction
Veterans Rd Culvert Construction
Veterans Rd Culvert Construction
Veterans Rd Culvert Construction
Veterans Rd Culvert Construction